The S.C. Electric & Gas Co. (SCE&G) announced Tuesday that significant progress has been made in building Reactor Unit 3 at the Virgil C. Summer Nuclear Generating Station in Fairfield County.
Within the same week, the CA04 module was installed and the reactor vessel arrived at the plant. The company said once the module is encased in concrete, the loading of the reactor vessel can be completed.
The plant will include two 1,117-megawatt AP1000 nuclear reactor units. The utility expects that with this addition, its energy generation will be more diversified. The company predicts that its generation output will be 30 percent nuclear, 30 percent natural gas, 30 percent coal and 10 percent split among hydro, solar and other renewable forms of energy.
Approximately 3,500 temporary positions have been facilitated through this construction project and 800 permanent positions will be available at the generating station once the reactors are completed. Unit 2 is expected to be operational in Aug. of 2019 and Unit 3 is expected to be online in May 2020.
SCE&G provides electricity for approximately 692,000 customers and natural gas to approximately 342,000 clients.
SCE&G outlines progress on Summer Unit 3
More Stories
- DUKE ENERGY: Renewables acquires 144-MWac Pflugerville Solar project in Texas from Canadian Solar
- WINDESCO: WeBoost Platform Increases Annual Output by $3,000 per Megawatts for Longroad Energy's 145 Megawatts Acquired Wind Plant
- ACWA POWER: Signs three agreements for the first foreign investment based independent wind power project in Azerbaijan
- CAPITAL DYNAMICS: Exits 108-Megawatt Beacon II and V Solar Portfolio in Kern County, California
- KEMP: Combines 4th Generation Technology to Produce Offshore Wind Power Structures
- TRANSALTA RENEWABLES: Announces the Acquisition of 303 MW Portfolio including 274 MW of Wind from TransAlta Corporation
- DOMINION ENERGY: Files Construction and Operations Plan for Coastal Virginia Offshore Wind Project
- DYNAMIC ENERGY: Celebrates Completion of Solar Project for The Miyoshi Kasei Group
- Dominion Energy, BrightSuite Partner with Sun Tribe to Bring Solar to 21 Schools Across Virginia
- GEORGIA POWER: Receives first nuclear fuel shipment for Vogtle Unit 3