NRC probes Callaway Nuclear Station in wake of control-valve failures

Image
-
0Comments

The U.S. Nuclear Regulatory Commission (NRC) said on Monday that it has launched a special investigation into the circumstances that led to a recent shutdown of the Callaway Nuclear Station near Fulton, Missouri, after the failure of three control valves.

The report said that on Aug. 11 during a planned startup, the plant, operated by Ameren, behaved normally until operators attempted to start motor-driven water pumps, when control valves failed to operate. The NRC said three out of four valves failed to operate. The valves regulate water flow into the steam generators.

“The purpose of this special inspection is to better understand the circumstances surrounding the valve failures, determine if the licensee’s extent-of-condition review was sufficiently comprehensive and review the licensee’s corrective actions to ensure that the causes of the failures have been effectively addressed,” NRC Region IV Administrator Marc Dapas said.

The NRC said circuitry in the valves had been modified in 2014 and that this is thought to have created a flaw in the valves’ operability.

Over a week-long period, NRC inspectors will be evaluating the facility’s maintenance, testing practices, the design changes to the valves and what corrective actions are needed in relations  to this specific issue.



Leave a Reply

Your email address will not be published. Required fields are marked *

Related

WINDESCO: WeBoost Platform Increases Annual Output by $3,000 per Megawatts for Longroad Energy’s 145 Megawatts Acquired Wind Plant

WINDESCO: WeBoost Platform Increases Annual Output by $3,000 per Megawatts for Longroad Energy’s 145 Megawatts Acquired Wind Plant

WindESCo Helps Longroad Energy Optimize Wind Asset Performance to Unlock $430,000 in Annual Revenue

ACWA POWER: Signs three agreements for the first foreign investment based independent wind power project in Azerbaijan

ACWA POWER: Signs three agreements for the first foreign investment based independent wind power project in Azerbaijan

Following the signing of the implementation agreement for the $300 million Independent Power Project in January 2020, and under the patronage of the Ministry of Energy in Saudi Arabia, ACWA Power today executed the official agreements for the 240 MW wind power project that will be located in the Absheron and Khizi regions.

CAPITAL DYNAMICS: Exits 108-Megawatt Beacon II and V Solar Portfolio in Kern County, California

CAPITAL DYNAMICS: Exits 108-Megawatt Beacon II and V Solar Portfolio in Kern County, California

Capital Dynamics, an independent global private asset management firm, completed the sale of a majority interest in its Beacon portfolio to TortoiseEcofin and S&B USA Energy. Each buyer has acquired a 49.5% ownership of the portfolio. Capital Dynamics retains a minority stake of 1%.

Trending

The Weekly Newsletter

Sign-up for the Weekly Newsletter from Power News Wire.