NRC begins River Bend nuclear plant inspection after lightning strike

River Bend Nuclear Station Courtesy of Entergy Corp.
River Bend Nuclear Station - Courtesy of Entergy Corp.
0Comments

The U.S. Nuclear Regulatory Commission (NRC) began a special inspection of the River Bend Nuclear Station near St. Francisville, Louisiana, this week.

An unplanned shutdown of the plant, operated by Entergy Operations Inc., was triggered on Jan. 9 after a lightning strike caused a surge in off-site power supplies. NRC staff will analyze the incident on site to examine

 the plant’s root-cause analysis, analyze any maintenance done on plant systems and judge the adequacy of corrective actions that were taken.

The NRC said a full report of this weeklong investigation will be released approximately 45 days after the completion of the investigation.

The NRC said post-lightning strike actions by the plant operators were taken, such as putting the plant in safe-shutdown mode. The next day, shutdown cooling was unavailable for one hour due to operational errors, the NRC said in a statement.

“The purpose of this special inspection is to better understand the circumstances surrounding the loss of shutdown cooling, determine if operator response was appropriate and review the licensee’s corrective actions to ensure that the cause of the event, including associated equipment problems and any contributing operator actions, have been effectively addressed,” NRC Region IV Administrator Marc Dapas said.



Related

WINDESCO: WeBoost Platform Increases Annual Output by $3,000 per Megawatts for Longroad Energy’s 145 Megawatts Acquired Wind Plant

WINDESCO: WeBoost Platform Increases Annual Output by $3,000 per Megawatts for Longroad Energy’s 145 Megawatts Acquired Wind Plant

WindESCo Helps Longroad Energy Optimize Wind Asset Performance to Unlock $430,000 in Annual Revenue

ACWA POWER: Signs three agreements for the first foreign investment based independent wind power project in Azerbaijan

ACWA POWER: Signs three agreements for the first foreign investment based independent wind power project in Azerbaijan

Following the signing of the implementation agreement for the $300 million Independent Power Project in January 2020, and under the patronage of the Ministry of Energy in Saudi Arabia, ACWA Power today executed the official agreements for the 240 MW wind power project that will be located in the Absheron and Khizi regions.

CAPITAL DYNAMICS: Exits 108-Megawatt Beacon II and V Solar Portfolio in Kern County, California

CAPITAL DYNAMICS: Exits 108-Megawatt Beacon II and V Solar Portfolio in Kern County, California

Capital Dynamics, an independent global private asset management firm, completed the sale of a majority interest in its Beacon portfolio to TortoiseEcofin and S&B USA Energy. Each buyer has acquired a 49.5% ownership of the portfolio. Capital Dynamics retains a minority stake of 1%.

Trending

The Weekly Newsletter

Sign-up for the Weekly Newsletter from Power News Wire.