GOLAR LNG LIMITED: Golar Power reaches Financial Closing on 1.5GW Sergipe Power Project

Image
-
0Comments

Golar LNG Limited issued the following announcement on April 19.

Golar LNG Limited (“Golar”) announces today that Golar Power Limited (“Golar Power”), a joint venture with Stonepeak Infrastructure Partners, has reached financial closing on the 1.5GW Porto de Sergipe I Power Project (the “Project” or “Sergipe TPP”). Located in Sergipe, NNE of Brazil, the Project will be the largest and most efficient thermoelectric power plant in Latin America and the Caribbean upon its completion.

CELSE (Centrais Elétricas de Sergipe S.A.), the Project company 50% controlled by Golar Power, will receive US$1.340 billion under a non-recourse project financing structure. Total proceeds from the financing will be used to fund remaining capital expenditures of the Project, including: the 1.5GW Power Plant, a dedicated 34km 500KV high-voltage transmission line, and associated gas pipeline and mooring infrastructure required for the integrated LNG import terminal facility.

Total Project capex including taxes and financing costs is estimated at US$1.740 billion. The total equity contribution of approximately US$400 million has been fully paid-in and includes US$123 million in cash reserve accounts that were pre-funded by the project sponsors. The power project will generate a forecasted annual EBITDA of US$323 million at current exchange rates, prior to any dispatch. Commencement of power station commercial operations is scheduled for January 1st, 2020. Payments under the executed PPA are inflation indexed and provide for pass-through of fuel costs to the PPA counterparties.

Golar Power CEO Eduardo Antonello commented: “This innovative financing represents a key milestone in the development of Golar Power infrastructure projects globally, establishing a precedent for financing in local currency in support of projects receiving revenues in local currency which are adjusted based on inflation. The Project bond issuance has attracted the interest of multiple international investors and opens a new horizon of opportunities for infrastructure development. With this experience, we believe Golar Power is uniquely positioned to help deliver these opportunities globally to new and underserved customers and geographies.

With the Sergipe TPP we have developed a fully flexible and highly efficient natural gas fired plant that will enable Brazil to increase its energy security while continuing to expand its development of renewable energy resources, including solar and wind.”

In connection with financial close of the Project, Golar Power has also executed final agreements with CELSE to charter the Golar Nanook, a fully customized new-build 170,000m3 FSRU, for 26 years. The annual EBITDA contribution for Golar Power is currently projected to be approximately US$41 million, with annual escalation indexed to US-CPI, and upside potential for Golar Power through use of the remaining two-thirds of FSRU capacity not utilized by the Project. The terminal is located in a strategic entry point to the NNE of Brazil, within 20km of the main gas distribution network, and has the potential to unlock future LNG distribution opportunities into Brazil.

Original source can be found here.



Leave a Reply

Your email address will not be published. Required fields are marked *

Related

WINDESCO: WeBoost Platform Increases Annual Output by $3,000 per Megawatts for Longroad Energy’s 145 Megawatts Acquired Wind Plant

WINDESCO: WeBoost Platform Increases Annual Output by $3,000 per Megawatts for Longroad Energy’s 145 Megawatts Acquired Wind Plant

WindESCo Helps Longroad Energy Optimize Wind Asset Performance to Unlock $430,000 in Annual Revenue

ACWA POWER: Signs three agreements for the first foreign investment based independent wind power project in Azerbaijan

ACWA POWER: Signs three agreements for the first foreign investment based independent wind power project in Azerbaijan

Following the signing of the implementation agreement for the $300 million Independent Power Project in January 2020, and under the patronage of the Ministry of Energy in Saudi Arabia, ACWA Power today executed the official agreements for the 240 MW wind power project that will be located in the Absheron and Khizi regions.

CAPITAL DYNAMICS: Exits 108-Megawatt Beacon II and V Solar Portfolio in Kern County, California

CAPITAL DYNAMICS: Exits 108-Megawatt Beacon II and V Solar Portfolio in Kern County, California

Capital Dynamics, an independent global private asset management firm, completed the sale of a majority interest in its Beacon portfolio to TortoiseEcofin and S&B USA Energy. Each buyer has acquired a 49.5% ownership of the portfolio. Capital Dynamics retains a minority stake of 1%.

Trending

The Weekly Newsletter

Sign-up for the Weekly Newsletter from Power News Wire.