Georgia Power has received unanimous approval from the Georgia Public Service Commission (PSC) concerning costs associated with the construction of the expansion of the Vogtle Electric Generating Plant, the company announced on Tuesday.

This was achieved within the 12th Vogtle Construction Monitoring Report, which indicated approximately $169 million in capital and construction costs. The expansion of the plant involves the construction of two nuclear reactor units that will join the two plants that are currently operating at the site just outside of Waynesboro.

Within this report, the company also informed PSC members of milestones that have been achieved in the construction of the plant. Reports are submitted to the PSC board every six months and this report indicates capital and costs up until Dec. 31 of this past year. Since the project’s inception, capital investments have reached approximately $2.96 billion.

Recently, the company reported that earlier in August the Vogtle Unit 3 had its CA01 module installed, which has been the heaviest lift operation at the site. Prior to that the containment vessel and structural wall module CA05 has also been installed at Unit 3.

The two nuclear generators have an estimated generation capacity rated at 1,100 megawatts of electricity.



Leave a Reply

Your email address will not be published. Required fields are marked *

Related

WINDESCO: WeBoost Platform Increases Annual Output by $3,000 per Megawatts for Longroad Energy’s 145 Megawatts Acquired Wind Plant

WINDESCO: WeBoost Platform Increases Annual Output by $3,000 per Megawatts for Longroad Energy’s 145 Megawatts Acquired Wind Plant

WindESCo Helps Longroad Energy Optimize Wind Asset Performance to Unlock $430,000 in Annual Revenue

ACWA POWER: Signs three agreements for the first foreign investment based independent wind power project in Azerbaijan

ACWA POWER: Signs three agreements for the first foreign investment based independent wind power project in Azerbaijan

Following the signing of the implementation agreement for the $300 million Independent Power Project in January 2020, and under the patronage of the Ministry of Energy in Saudi Arabia, ACWA Power today executed the official agreements for the 240 MW wind power project that will be located in the Absheron and Khizi regions.

CAPITAL DYNAMICS: Exits 108-Megawatt Beacon II and V Solar Portfolio in Kern County, California

CAPITAL DYNAMICS: Exits 108-Megawatt Beacon II and V Solar Portfolio in Kern County, California

Capital Dynamics, an independent global private asset management firm, completed the sale of a majority interest in its Beacon portfolio to TortoiseEcofin and S&B USA Energy. Each buyer has acquired a 49.5% ownership of the portfolio. Capital Dynamics retains a minority stake of 1%.

Trending

The Weekly Newsletter

Sign-up for the Weekly Newsletter from Power News Wire.